Release 3.0 Overall Goals

There are several motivations for release 3.0 of Cytoscape, but the overriding theme of the release is to refactor/redesign the code so that things become easier. Things in this case has several specific meanings:

Desired Features

Refactoring Strategy

Rather than rewriting Cytoscape from scratch we intend to refactor the existing code base. Since we already have a working version of Cytoscape that suits many people's needs quite well, a central tenet of the refactoring process will be to maintain a working version of Cytoscape. That means that each time a change is made (i.e. code checked into the trunk), all unit tests should pass and Cytoscape's main functionality should still work. This will be an iterative process with many small changes, rather than a few large ones. The hope is that with this process we will not lose functionality as we make changes.

Rough module refactoring plan

The general plan is to begin by cleaning up the existing code base and modularize what we can while changing as little as possible. The goal is to establish the modules that comprise Cytoscape and the dependencies between them. Once we have a coherent structure of existing code, we can begin redesigning modules to suit our new requirements.

Prepare the existing code base for refactoring.

Once the existing code base has been cleaned up, we can begin our redesign efforts for 3.0. The general strategy will be to work from the bottom up. That is to say, begin with the modules at the base of the dependency graph that all other modules depend on. This means work on Networks and Attributes first, followed by the View and on up through the dependency graph.

A time schedule has been put together to allow for time to discuss and plan each module and provide some end dates for when each discussion should be finished and implementation can begin. As much as possible we will work to adhere to this to allow 3.0 to be released in a reasonable time frame. Start dates will be added after 2.6 is officially released.

See attachment for a nicely formatted version of the table below that includes time estimates and potential dates. attachment:Cyto3ProjectPlan.xls

ID Name Description
4 Modular System Milestone 1 - Layer current code base
5 Separate code into layers Per the RFC's modules for Graph model, View model, IO, View (presentation), Application, Command
6 Introduce temporary interfaces Starting with the graph model, write interfaces to allow other layers to access the graph model and remove all dependencies to classes outside the graph model. Once it has no dependencies, work on other layers to ensure dependencies are correct and unidirectional.
7 Unit test/documentation Per each layer, multiple people can work on this
8 Build Process - Maven Mavenize separate layers to build modularly again start from the graph model
9 Merge 2.6 bug changes Merge 2.6 changes into 3.0 branch
10 Recode Core Interfaces Milestone 2 - Replace temporary interfaces with stable, planned interfaces. First relayered system finished
11 Graph Model Use what's been learned from Step 1 to write use cases specific to the graph model as used within core code. Ideally 3-10 use cases should be identified
12 Use Cases Based on use cases develop a graph model interface for core usage. Add indexing pattern for fast graph iteration.
13 Interface Development
14 Plugin Interface Development Determine if a separate Plugin interface is required to limit access to specific parts of the graph model.
15 Interface Implementation
16 Unit test/documentation Each layer's interface needs to include unit tests and documentation in order to be considered finished
17 View Model Similar to Step 8, the difference being that this layer deals only in the persistable visual data that needs to be stored (but not the actual presentation layer)
18 Use Cases 3-10 use cases
19 Interface Development Provide for view models that are persistable but not dependent on the actual presentation.
20 Interface Implementation
21 Unit test/documentation
22 IO
23 Use Cases
24 Interface Development
25 Plugin Interface Development
26 Interface Implementation
27 Unit test/documentation
28 View (Presentation)
29 Use Cases
30 Interface Development ??? Not sure about this one. The presentation layer may require more time and will be adjusted later
31 Plugin Interface Development
32 Interface Implementation
33 Unit test/documentation
34 Command
35 Use Cases
36 Interface Development
37 Plugin Interface Development
38 Interface Implementation
39 Unit test/documentation
40 Application
41 Use Cases
42 Interface Development
43 Plugin Interface Development
44 Interface Implementation
45 Unit test/documentation
46 Examine further componentization (OSGi)

Discussions

Timeline

Release Date: TBD